By order of the head of the regional state administration, head of the regional military administration dated 09.05.2025 No. 329/5-25 “On measures to prepare housing and communal services facilities in the region for operation in the autumn-winter period of 2025-2026,” organizational and technical measures were approved to prepare housing and communal services facilities in the region for operation in the next heating season.
Due to the military aggression of the Russian Federation against Ukraine, active hostilities continue in the region, part of the region is under temporary occupation, surrounded (blockaded), and the rest is under shelling or threat of shelling, which significantly complicates the implementation of the measures specified in the order.
According to the recommendations of the Ministry of Community and Territorial Development of Ukraine, the level of readiness of housing and communal services and social facilities as of August 1, 2025, should be 60%.
According to operational information from district state administrations, district military administrations, in the settlements of the region located in the territory controlled by the Ukrainian authorities, and where it is possible to do so under martial law,
as of August 1, 2025, the level of readiness of the region's facilities is 57% or 2,035 facilities out of the planned 3,556, namely:
1,753 residential buildings, or 58% of the planned 3,045 units, have been comprehensively prepared in the housing stock;
the readiness of social facilities is 62% (115 units out of 186), including 48% of healthcare facilities (33 units out of 69);
In the heating sector:
- readiness of boiler rooms – 47% (76 out of the planned 161);
- preparation of heating networks – 51% (206 km out of 407.4 km);
- replacement of heating networks – 17.5% (2 km out of the planned 11.1 km);
in the water supply and sewerage sector:
- repair or replacement of water supply networks – 73% (17.7 km out of the planned 24.2 km);
- repair or replacement of sewerage networks – 53% (7.8 km out of the planned 14.8 km);
diness of water pumping stations – 63% (43 out of 68);
- readiness of sewerage pumping stations – 60% (42 out of 70 units);
in road and bridge infrastructure:
- major and routine repairs of city roads – 73% (99.4 thousand m2 out of the planned 136.7 thousand m2);
- preparation of specialized equipment – 14% (11 units out of the planned 81 units).
More than UAH 136.2 million has been spent on the specified scope of work, in particular:
- for heat supply facilities – UAH 17.5 million,
- for water supply and sanitation facilities – UAH 13.0 million,
- for housing and social facilities – UAH 10.8 million,
- for road maintenance – UAH 94.9 million.
Work is continuing on preparing housing and communal services and social facilities in the region for the autumn-winter period of 2025-2026 under martial law, taking into account security considerations.